The challenge - Improve product quality to achieve IATF 16949 Certification
Gardner Denver has selected Sorion for the implementation of a complete production control solution to guide, control and verify the assembly operations at the customer’s compressor manufacturing facility in Redditch, Worcestershire.
The goal of the project was to improve the quality of the assembly processes to help the customer achieve IATF (International Automotive Task Force) 16949 certification.
The brief included incorporating operator control workstations, integration with Gardner Denver build schedules and overall traceability with archiving of historical data for the manufactured product.
The solution
The compressor assembly line has 9 process areas: 5 assembly stations, 2 test stations, 1 kitting station, 1 dispatch station and 1 rework station.
A management station is used for generating the build schedules on the assembly line. Each workstation uses a separate all-in-one PC touch panel running Sextans-RT, Sorion’s process control and test application.
Technologies Implemented at Gardner Denver
Since rolling out the solution, process accuracy and quality have increased significantly. The Sorion system also helped us achieve the full traceability required by the IATF 16949 automotive standard.